Progress on the construction of the viaduct in Krosno – support foundations are ready, work on retaining walls and embankment stabilization is in progress

KROSNO ‼️
👉🫡 We are returning to the construction site in Krosno, where at the beginning of October we finished making large-diameter piles and started work on reinforcing and concreting the foundations. Currently, these elements are ready for two of the five supports of the new viaduct over railway line no. 108. 🛤
Taking advantage of the favorable weather, we are also carrying out intensive work related to stabilizing the lower layers of the road embankment and building retaining walls made of reinforced soil.🧱 We have already installed 2,000 m2 of prefabricated panels, and the total is approximately 4,400 m2 of retaining wall panels.
We invite you to our gallery, where you can see the progress of the work. 👏👍